DESIGN OF RECTANGULAR OVER HEAD WATER TANK CLOSE FROM TOP 
RESTING ON COLUMNS

 

   

DESIGN RESULT

 
DESIGN OF RECTANGULAR OVER HEAD WATER TANK CLOSE FROM TOP RESTING ON COLUMNS

Clear Height of Tank in M (h1): 2.0

Width of Base in M (W): 3.0

Length of Base Slab in M (L): 3.5

Thickness of Roof Slab in M (t1): 0.125

Thickness of Stem in M (t2): 0.15

Thickness of Base Slab in M (t3): 0.25

Dia of Vertical Reinforcement: 12

Dia of Horizontal Reinforcement: 12

Concrete Grade: M30

Steel Strength (fy) [N/MM2]: 415

Dia of Roof Reinforcement: 8

Dia of Wall (As Beam) Reinforcement: 20

------------------------------------------------------------------

Overall Tank Length in M = 7.38

Overall Tank Width in M = 3.25

Total Max. Load of Tank in Tons = 78.01

Total Load of Tank From Roof Slab / Platform in Tons = 11.09

Total Load of Tank Stem in Tons = 9.02

Total Load of Tank Base in Tons = 16.9

Total Load of Tank Water in Tons = 41

Empty Load of Tank in Tons = 37.01

------------------------------------------------------------------

Prop. Cantilever Stem BM on Water Face in t-m = 0.53

Prop. Cantilever Equivalent Stem BM on Water Face in t-m = 0.56

Prop. Cantilever Stem BM on Away from Water Face in t-m = 0.24

Prop. Cantilever Equivalent Stem BM Away from Water Face in t-m = 0.27

Max. Stem SF in tons = 1.6

Max. Equivalent Horizontal Stem BM in t-m = 0.38

Max. Vertical Stem Compression in tons = 1.21

Max. Horizontal Stem Tension in tons = 0.91

------------------------------------------------------------------

Max. BM in Base (T & B) in t-m = 1.83

Max. Equivalent BM (T & B) in Base in t-m = 1.71

Max. SF in Base in tons = 3.29

Max. Tension in Base in tons = 1.6

------------------------------------------------------------------

Max. BM in Roof (T & B) in t-m = 0.37

Max. Equivalent BM (T & B) in Roof in t-m = 0.37

Max. SF in Roof in tons = 1.02

Max. Tension in Roof in tons = 0.4

------------------------------------------------------------------

Max. BM in Wall (Acting as Beam) in t-m = 31.66

Max. SF in Wall (Acting as Beam) in tons = 6.36

------------------------------------------------------------------

Actual Bending Tensile Stress in Stem in Kg/CM2 = 14.13

Permissible Bending Tensile Stress in Stem in Kg/CM2 = 20

------------------------------------------------------------------

Provide Vertical Stem bars at Water Face as dia 12 MM @ 150 MM c/c

Provide Vertical Stem bars Away from Water Face as dia 12 MM @ 150 MM c/c

Provide Horizontal Stem bars at Each face as dia 12 MM @ 150 MM c/c

------------------------------------------------------------------

Factored Shear Stress in Stem in Kg/CM2 = 2.4

Max. Permissible Shear Stress in Stem in Kg/CM2 = 36.7

Capacity of Stem Section in Shear in Tons = 3.97

------------------------------------------------------------------

Permissible Bending Tension in Base Slab in Kg/CM2 = 20

Actual Tensile Bending Stress in Base Slab in Kg/CM2 = 17.57

Permissible Direct Tensile Stress in Base Slab in Kg/CM2 = 15

Actual Direct Tensile Stress in Base Slab in Kg/CM2 = 0.64

Ratio is < 1.0 = 0.92

------------------------------------------------------------------

Provide Bothways Base Reinforcement at Water Face (Top) as dia 12 MM @ 135 MM c/c

Provide Bothways Base Reinforcement at Bottom Face as dia 12 MM @ 135 MM c/c

Factored Shear Stress in Base in Kg/CM2 = 2.47

Max. Permissible Shear Stress in Base in Kg/CM2 = 36.7

Capacity of Base Section in Shear in Tons = 6.21

------------------------------------------------------------------

Provide Roof Reinforcement along Shorter Direction at Bottom & at Support Top as dia 8 MM @ 112 MM c/c

Provide Roof Reinforcement along Longer Direction at Bottom & at Support Top as dia 8 MM @ 125 MM c/c

Factored Shear Stress in Roof in Kg/CM2 = 2.04

Max. Permissible Shear Stress in Roof in Kg/CM2 = 36.7

Capacity of Roof Section in Shear in Tons = 2.71

------------------------------------------------------------------

Provide Wall as Beam Reinforcement at Bottom as dia 20 MM - 2 Nos

Provide Wall as Beam Reinforcement at Top as dia 20 MM - 2 Nos

Provide Links as dia 10 MM @ 300 MM c/c through out Wall-Beam.

Factored Shear Stress in Wall-Beam in Kg/CM2 = 2.44

Max. Permissible Shear Stress in Wall-Beam in Kg/CM2 = 36.7

Capacity of Wall-Beam Section in Shear in Tons = 26.55

------------------------------------------------------------------

Total Concrete Quantity Consumed by Tank in M3 = 13.21

Total Steel Quantity Consumed by Tank in Tons = 2.36

Clear Cover to Reinforcement is taken as 40 MM : Load Factor = 1.5

For Construction Joint, Corner & Haunch Reinforcement details refer Standards.

Provide Minimum Haunch as 300 * 300 MM between Wall and Base.

Provide Haunch Reinforcement as dia 12 MM @ 150 MM c/c

Provide a Single 16 MM dia bar at Center of Haunch.

Concrete Grade for Roof Slab is same as that of Tank.

Tank is Designed as Horizontal Spanning & as Propped Cantilever.

Tank shall be Tested for water tightness only after Casting the roof Slab.

Load on Each Column in Tons = 19.5

Minimum Column Size shall be 300 * 300 MM.

ooooooooooooooooooo fini oooooooooooooooooooooooo