CPWD CONSTRUCTION COST INDEX CALCULATION

COST INDEX OF PLACE - X BASED ON PLINTH AREA RATE 01.01.92
Enter New Rate at the Time of Cost Index Revision & Press Calculate Button.

S
No.
Description Unit Rate as on 1.1.92
(r)
Weightage
(w)
Enter New Rate at the Time of Cost Index Revision  (z) Cost index as on 
New Date
(cx) = w x z ÷ r
1 BRICKS (in Nos) 1000 800.00 16.0
2 SAND CUM 146.6 4.0
3 CEMENT QTL 213.28 19.0
4 AGGREGATE CUM 185.0 4.5
5 TIMBER CUM 12334.0 9.5
6 REINFORCEMENT QTL 1342.5 23.5
7 MASON EACH 55.71 8.0
8 CARPENTER EACH 55.71 3.5
9 MALE LABOUR EACH 34.3 12.0
        100 New Cost Index

                                   

 

Note:
1. The rate of bricks is the sum of 67 % rate of bricks and 33 % rate of stones. (1000 bricks is equivalent to 2.72 cum of stones).
2. The rate of sand is the sum of 67 % rate of coarse sand and 33 % rate of fine sand.
3. The rate of aggregate is the sum of the 50 % rate of 20 mm stone aggregates and 50 % rate of 40mm stone aggregates.
4. The rate of timber is the sum of 25 % rate of II class teak wood and 75 % rate of country wood.
5. The rate of steel is the sum of 50 % issue rate of 8 to10 mm Tor steel bars and 50 % issue rate of 12 to 16 mm Tor steel bars.
6. The rate of mason is 50 % rate of  I Class mason and 50 % rate of  II Class mason excluding paid holidays.
7. The rate of carpenter is 50 % rate of  I class carpenter and 50 % rate of 11 class carpenter excluding paid holidays.
8. The rate of Male Labour is the rate of  Male Labour excluding paid holidays and 50 % rate of male Labour and 50 % rate of  female Labour.
This is a sample program from Super Real Valuation Software. For more info Contact:
Mr. Yusuf A. Agboatwala,
1802, Jamuna Amrut, 219, Patel Estate,
S. V. Road, Jogeshwari (West), 
Mumbai 400102.
Phone: 26783525
Cell: 9820792254
URL: www.supercivilcd.com 
Email: yaa@supercivilcd.com